BUILDING INSPECTIONS...
Please contact the Building Services Division at
638-3366 PRIOR to 3 p.m. to schedule a NEXT BUSINESS
DAY inspection. Requests received AFTER 3
p.m. will be scheduled for the second business work
day. REMEMBER: Your building PERMIT
NUMBER is required to schedule an inspection.
If you wish to speak with your inspector, please call
410.638.3366 between 7:30am to 8:00am and 3:00pm to 4:00pm
INSPECTIONS: The Code requires one
copy of the approved plans and specifications together
with the permit to be kept at the site of operation at all
times during the progress of the work. it is the
responsibility of the person obtaining the permit to
notify the building official when work is ready for
inspection and no work should be covered before it has
been inspected and approved. Requests for inspection
are required in accordance with the following schedule:
- FOOTING: Prior to pouring concrete,
after cleaning out and grade stakes in place, stone
entrance (minimum of 10 feet wide by 25 feet long)
installed and a silt-fence installed around the lowest
perimeter of disturbance.
- FOUNDATION: Prior to backfill, after
parging and drain tile if outside. Not required
on garage.
- SLAB/DRAIN TILE: Prior to pouring slab
and drain tile if inside. Not required on
garage.
- FRAMING: Prior to application of
insulation and after Plumbing and Electrical
inspection.
- INSULATION: Prior to application in
interior finish.
- FINAL: Prior to occupancy (TYPE 1 -
OUTSIDE ITEMS ONLY!)
- USE AND OCCUPANCY CERTIFICATE (U&O):
Required prior to occupancy.
- MOBILE HOMES, SALES TRAILERS: Contact
Jim Moore at 410.638.3385 for inspections.
- Display property address clearly visible from
roadway prior to final inspection.
- Stabilization of lot must be completed prior to
issuance of any type of Use and Occupancy Certificate.
- All electrical and plumbing work requires a separate
permit to be obtained by a licensed Master
Electrician/Plumber.
NOTE
Your building permit is valid for twelve
months from the date of issuance. "Any permit
issued shall become invalid if the authorized work is not
commenced and diligently pursued within twelve (12) months
after issuance or is suspended or abandoned for a period
of six (6) months after the work has commenced.
Another permit, upon application, may be issued if the
applicant can demonstrate that construction will commence
within six (6) months after reissuance and will be
diligently pursued to completion."
DILIGENTLY PURSUED IS INTERPRETED AS, "AN INSPECTION
OBTAINED WITHIN SIX MONTHS FROM THE DATE OF THE PREVIOUS
INSPECTION".
A final Use and Occupancy Certificate is
required and must be issued after completion of your
project and prior to occupancy.
A Use and Occupancy is required for ALL:
-
residential construction
-
commercial construction
Inspections are required during
construction and at completion. After all final
inspections are approved, a Use and Occupancy Certificate
will be issued by the Department of Inspections, Licenses
and Permits. There is no fee charged to issued the
certificate. However, if reinspection fees were
charged ($50 per reinspection) during construction, these
fees must be paid prior to issuance of a Use and Occupancy
Certificate.
To schedule a required inspection, please
call:
|
Agency |
Phone No. |
| Building Services |
410.638.3366 |
| Electrical Services |
410.638.3363 |
| Plumbing Services |
410.638.3215 |
| Health Department |
410.638.3499 (well &
septic) |
| Water & Sewer, DPW |
410.612.1612 (public facilities) |
| Housing Services |
410.638.3385 (mobile
homes/office trailers) |
Health Department and Water and Sewer approvals
are required for all commercial permits.
To check on the status of, or to pick-up a
Use and Occupancy Certificate, please call 410.638.3305 or
go to our On-Line
Permit Inquiry site.
|